Dudley Street Basement Excavation

Geotech was sub-contracted to construct the basement retention for the Market Square Condo Apartments.

The work included:

  • Manufacture, supply and installation of 78no. precast soldier piles (450mm*450mm*average length 7m).
  • Design, supply and install 147no. 400kN temporary ground anchors.
  • Construction of 1070m2 Shotcrete wall (200mm thick) including supply of all materials.
  • Bulk excavation and disposal off site (15,000 m3 solid)
  • Detailed excavation of base slabs and footings