Dam Remediation
Tunnel Construction
Basement Excavation
Slope Stabilisation
Tunnel Remediation
 
 
 
 
 
 
 
 
 
 
 
 
 
 

 

 

 

 Tunnel Construction


Flemington Racecourse Tunnel Project

The Flemington Racecourse Under track Horse & Vehicle Tunnel Contract was awarded to Geotechnical Engineering by the Victorian Racing Committee (VRC) in August 2002. The Project value was approximately $6m. Tunnel structure including ramps is approximately 400m long, with the tunnel section approximately 200m long. The tunnel which is 11m wide and 4.7m high is primarily to be used for horse access to training tracks on inside of the racecourse, however it can also accommodate three lanes of vehicle traffic for access to parking during racing carnivals.

Demanding construction deadlines were included in the contract to ensure that the VRC could continue to hold race meetings over the spring and summer racing carnivals.

The tunnel had to be constructed in soft saturated river delta material called Coode Island Silt. This silt extends to approximately 20 meters below the surface. This meant that special design and construction techniques had to be adopted. The final design solution was based on the use of sheet piles driven into the soft ground with the use of reinforced concrete to form the roof and floor while the internal walls were constructed using structural shotcrete.

Most of the sheet piles were driven to a depth of 15m. Every sixth sheet was driven to refusal in underlying dense granular material, called Moray Street Gravel, at depths of 20-25m to support the tunnel. A patented beam called a Bonacci Beam® consisting of steel shells placed at 3.6m centres and a metal tray deck spanning between these steel shells was adopted to support the roof loads unpropped over 11m.

This steelwork also acted as formwork for the concrete placed on top of it. Bulk excavation to the final depth within the tunnel was carried out in 3.6m 'drives' progressively installing structural steel props to control the lateral movement of the sheet piles. After a drainage layer was laid down over the props, the permanent concrete floors were constructed, followed by the spraying of concrete walls to line the sheet piles. In some areas the active sides of the excavations adjacent to the cantilevered sheet piles were "laid back" to reduce the lateral load on the sheet piles. In other areas "dead men" anchors were installed to restrain the high cantilevered sections of sheet pile wall.

Geotech completed the works well ahead of time and completed all the civil construction activities without the need to engage sub-contactors.
 



Home  |  Company  |  Principle Areas of Activity  |  Major Projects  |  Contact us  |  Sitemap

 Copyright © 2004-2007 Geotech Pty Ltd. All rights reserved.