Burwood Brickworks is set to be a world leading retail & public space upon its completion. The approx. 12,700m2 space will comprise of retail outlets, public amenities and will house approx. 2,000 residents – the centre is seeking to be a part of the world’s most sustainable shopping districts due to its unique construction.

To allow excavation and then development on the 78 Middleborough Rd property, a retaining wall was required along the perimeter and adjacent RSPCA property.

Our Role

Geotech’s work involved the construction of a 300m long by up to 10m high retaining wall.
The detailed scope of works included:

  • Drilling, inserting, then grouting 800no. 4.5m X 25mm galvanised steel soil nails into siltstone wall at 1.5m spacing
  • Detailed excavation around the nails to ensure a flat and uniform wall surface
  • Fixing strip drains between the nails to prevent any water undermining the wall
  • Fixing RL81 mesh along the wall and tying onto the nails
  • Shotcrete spraying the wall 180mm thick
  • Creating a 300m spoon drain along the top to allow drainage into pits at either end of wall

Disciplines covered

  • Soil nail wall

Contáctanos. Nuestro horario de oficina:
Lun - Vie 8:30 - 17:00

HEAD OFFICE - MELBOURNE

11 Eastern Rd, South Melbourne VIC 3205

padding-bottom: 5%; "> GEOTECH OFFICE LOCATIONS

HEAD OFFICE - MELBOURNE

174 Turner Street, Port Melbourne, VIC 3207

PERTH

Level 3, 195 Great Eastern Highway, Belmont, Western Australia 6104

+61 8 9488 8212

BRISBANE

Level 2, 100 Melbourne Street, South Brisbane, Queensland 4101

SYDNEY

Level 2, 55 Harrington Street, The Rocks, New South Wales 2000

Síguenos

Suscribir

Podría interesarte recibir información, noticias, alertas de nuestra parte...

Derechos reservados © 2020 Geotechnical Engineering.