The Melbourne Metro Tunnel Project involves the construction of two new tunnels to free up space in the congested city loop, the implementation of this project will increase the frequency of trains and facilitate the daily commute of many passengers.
The design for the CBD North Station includes a trinocular cavern that is 290m long with a span of 22m and a height of 19m.
In addition to the design and construction of 72 no. solider piles, Geotech were engaged to carryout open hole piling at the adjacent ancillary building located at the West Franklin St shaft.
Due to the site’s complex geotechnical conditions and the abrasive nature of the sandstone beds, Geotech had to be mindful of the sensitive location to avoid construction vibrations and disruptions to adjacent infrastructure.
Contáctanos. Nuestro horario de oficina:
Lun - Vie 8:30 - 17:00
HEAD OFFICE - MELBOURNE
11 Eastern Rd, South Melbourne VIC 3205
padding-bottom: 5%; "> GEOTECH OFFICE LOCATIONSHEAD OFFICE - MELBOURNE
174 Turner Street, Port Melbourne, VIC 3207
PERTH
Level 3, 195 Great Eastern Highway, Belmont, Western Australia 6104
+61 8 9488 8212
BRISBANE
Level 2, 100 Melbourne Street, South Brisbane, Queensland 4101
SYDNEY
Level 2, 55 Harrington Street, The Rocks, New South Wales 2000